← JD Portal
Jaber Development  ·  Cost Analytics

What each dollar bought

Quantities, unit rates, QS comparison and estimating — tied to the Jaber Dev ledger
As at
Cost to 31 Oct 2026 Ledger of 6 Nov 2026 · November 2026 not included
Cost basis

Key points

    From total project cost to construction cost

    Construction cost is the main focus of this report; the rest (permits, land, sales, fees) is shown here for the total picture.

    How much of the cost is measured

    By category. Light bar = cost; middle = backed by an invoice or statement; dark = has a quantity and a price. The % is the share with a unit rate.

    Build-up over time

    How to read this page
    • Every item bought with a quantity, grouped by category → sub-category. Each sub-category shows its cost and how much of it is measured, then its items.
    • Average rate = total paid before VAT ÷ quantity. Latest rate = the most recent purchase. Best rate = the lowest price paid, and by whom.
    • The coloured % beside the rate shows how much of that sub-category's cost the rate stands for: green 80% and above, amber 50–80%, red below 50%.
    • Click an item to see its price history underneath.

    Item cost analysis

    How to read this page
    • The QS (Table of Quantities) lists the quantities the building needs. It has no prices.
    • Supplied = material bought (e.g. ready-mix, blocks, steel). Labour = work billed on the engineer's statements (e.g. concrete placing pay units, blocks laid, plastering).
    • % of QS: under 100% = still to come; above 100% = more than the QS. A % is shown only when the actual and the QS measure the same element in the same unit; rows marked “not compared” or “not in QS” have no %. Labour % is a cross-check, not progress.
    • QS × actual rate (proposed) prices the QS quantity at the average rates paid. It is for discussion, not an approved budget.

    QS vs actual

    How to read this page
    • Both projects side by side, by category and sub-category. Projects differ in size, so compare the mix (each category's share of cost) and the cost per m² of slab, not only the amounts.
    • Cost per m² of slab uses the post-tensioned slab area as a stand-in for the built-up area, which is not available yet.
    • Rawshe Gardens 3688 is mostly at the structure stage; Twin Tower 3071 is into finishes. The full mix is comparable only when both are complete.
    • Cost + paid on account adds money paid to contractors in advance (not yet cost), e.g. MEP and aluminium.

    Cost by category

    Quantities and rates side by side

    Same measures in both projects, to 31 Oct 2026. Rates before VAT.

    Consumption ratios

    How much of one thing each project used per unit of another. Used by the Estimating page.
    How to use the calculators
    • Enter quantities in the white boxes. Each calculator prices them with the latest prices paid (the higher current price when the two projects pay differently) and the consumption ratios of the two projects.
    • Click Show lines to see and change any rate. Your changes are highlighted, and Reset returns to the actual rate.
    • Allow for price rise % raises every rate at once. Two totals are shown: at current rates and with your changes.
    • Results are proposed estimates, not approved budgets. They cover only the items listed; MEP, paint, gypsum, screed, doors and kitchens are not included.
    Rates are before VAT. Each rate shows its date, supplier and project; prices older than 6 months are marked.
    How to read this page
    • Every item bought on either project, with its latest price and supplier, the best current price (lower price when the two projects pay differently) and the trend since the first purchase.
    • Click an item for its detail and price history.

    Prices

    Contracts and advances at 31 Oct 2026

    Cost with no unit rate

    Cost that cannot be measured per unit: lump sums, fees, permits, land, and paid cost with no invoice. It is real cost; it has no quantity.

    Guide to the figures

    Plain definitions of every figure and term in this report.

    Total project cost
    All cost booked for the project in the Jaber Dev ledger up to 31 Oct 2026, incl. VAT. Every figure in this report adds up to it.
    Construction cost
    Total project cost less permits and studies, land, sales and brokers, fees / insurance / legal (incl. engineers' fees), taxes and miscellaneous. The default view of this report.
    Backed by a document
    Cost for which the invoice, statement or receipt was read line by line.
    Measured (unit rate)
    Cost whose documents show a quantity and a price, so a cost per m³, per tonne or per m² can be given.
    % measured
    Measured cost ÷ cost of the category. Near 100% means the rate stands for almost all of that spend. Green 80% and above, amber 50–80%, red below 50%.
    Paid on account
    Money paid to a contractor or supplier before an invoice or work report. It is not cost yet.
    Contract value
    The agreed amount of a contract, shown for information. Never added to cost.
    Before / incl. VAT
    Rates are before VAT so suppliers compare fairly; costs include VAT because that is what was paid.
    Average / latest / best rate
    Average = total before VAT ÷ quantity. Latest = the most recent purchase. Best = the lowest price paid on one document.
    Trend
    Change between the first and the latest price of an item (+ = dearer now).
    QS
    The quantity surveyor's Table of Quantities: what the building needs, by trade, without prices. Rawshe Gardens 3688 received; Twin Tower 3071 pending.
    Ready-mix concrete
    Concrete delivered from the plant (Sabeh Beton), by strength grade (e.g. 35 MPa) and stone size (10 or 20 mm).
    Concrete placing
    Pouring and finishing labour (incl. formwork), paid in contract pay units on Abou Al Fadel's statements: some sections count x1.5, elements under 1 m count as 1 m, and l.m lines count 1:1. Pay units are not the poured volume; the real labour cost per m³ poured = labour cost / ready-mix m³ delivered.
    Blinding
    Thin lean concrete layer poured under foundations.
    Rebar
    Steel reinforcing bars (D10 = 10 mm diameter), bought by the tonne.
    Post-tensioning
    Steel cables tensioned inside the slabs (Darwish Haddad), billed per m² of slab.
    Block laying / lintels
    Labour to build block walls (per m²); lintels and jambs are small concrete beams over openings (per linear metre).
    Proposed
    Any value built from a quantity × an actual rate (QS page, Estimating page). For discussion; not an approved budget.

    How the figures are built

    Cost = Project Cost debits less credits in the Jaber Dev ledger, to the last completed month. Documented cost is placed in the month of its invoice or statement; cost with no document in its ledger month. Rates use purchases only (returns reduce the quantity, not the price). Floors and blocks named on documents are not split in the actuals. The report is refreshed monthly after the month closes.